Welcome to MarTT's fotki!

Build

Ground breaking July 23, 2018. Sub slab Aug 8, 2013. Concrete pour Aug 13, 2018. Framing begins Aug 20, 2018. Windows in Aug 30, 2018. HVAC started Aug 31, 2018. Plumbing rough-in started Sept 4, 2018. Hardie Plank started Sept 11, 2018. Electrical started Sept 17, 2018. Garage door installed Sept 19, 2018. Roof shingles installed Sept 28, 2018. Painting exterior starts Sept 29, 2018 (wrong color). Insulation added Oct 4, 2018. Drywall started Oct 13, 2018 and completed Oct 19, 2018. Exterior repaint started Oct 19, 2018. Cabinets hung and Master Shower tile done Oct 26, 2018. Concrete driveway poured Nov 7, 2018. Home orientation Nov 19, 2018. Closing Nov 28, 2018. Moved in December 5, 2018.

20 Years of Indy Audi Club

Paul Lewer put together this memorable set of photos from various Indy Audi Club events. Uploaded March 29, 2020.

After Closing

Just a few things to take care of after closing, before, and during move in.

powered by Fotki